Concrete Footing Calculator

Concrete for strip or pad footings, including multiple footings and the total excavation volume.

Enter values

Results update as you type.

Result

Concrete required

5.832 m³

Per footing
5.4 m³
Cement bags (50 kg)
48
Sand
2.449 m³
Aggregate
4.899 m³
Excavation volume
6.21 m³
Spoil to remove (bulked 25%)
7.762 m³

About the Concrete Footing Calculator

Concrete for strip or pad footings, including multiple footings and the total excavation volume.

Also known as: strip footing calculator, pad footing concrete, foundation concrete, footing volume.

How to use this calculator

  1. Enter footing type, width, depth, waste allowance and the other fields.
  2. The result updates instantly as you type — press Calculate (or Enter) at any time.
  3. Review the breakdown shown under the main result.
  4. Use Copy result or Share to save the answer or send a link with your inputs.

Formula

Volume = length × width × depth × number of footings

Worked example

Using the values pre-filled in the calculator above:

  • Footing type: Strip footing
  • Total length = 30 m
  • Width = 0.6 m
  • Depth = 0.3 m
  • Waste allowance = 8 %
  • Mix ratio: 1 : 1.5 : 3 (M20) — 20 MPa — slabs and footings

the calculator returns:

  • Concrete required: 5.832 m³
  • Per footing: 5.4 m³
  • Cement bags (50 kg): 48
  • Sand: 2.449 m³